A refit is the point where a boat gets pulled apart, opened up, and put back together better than it was. It is also the point where budgets slip, schedules stretch, and good relationships between owners and yards turn sour. Strong yacht refit project management is the difference between a vessel that comes out of the shed close to budget and one that sits there for three extra months while the invoices keep arriving. This guide is written for owners, captains, and project managers who want to run a refit properly: how to define scope, choose the right contract, build a schedule that survives contact with reality, control variations, and hand the boat back ready to cruise.
Refits overrun. That is not pessimism, it is the base rate. For most yachts it is common for final costs to land 20 to 30 percent above the initial number, and for older vessels the overrun can be worse. The teams that stay closest to plan are not the ones with the fewest surprises. They are the ones who planned for surprises, wrote them into the budget, and had a process ready. Everything below is built around that idea.
Managing a yacht refit means owning the whole arc of the job: the spec, the contract, the money, the calendar, the trades, the quality, and the handover. On a small sailing yacht one person can hold all of that. On a 40 metre motor yacht going through paint, teak, and a systems overhaul, it becomes a full-time role for a dedicated project manager or a very organised captain. Either way the function is the same. Somebody has to be the single point of truth for what the job is, what it costs, when it finishes, and whether the work is good enough.
Professional project management is not free, but it is cheap relative to what it protects. On a larger refit an owner's representative typically costs 1 to 3 percent of the refit value, and a good one returns that fee many times over by catching pricing errors, holding the yard to the schedule, and stopping scope creep before it compounds. On a new build, management runs closer to 3 to 5 percent of build cost. If you are running the job yourself, treat those percentages as the value of the hours you are about to spend. The work is real whether or not you pay someone else to do it.
The first job of refit planning is to decide who does what. Who signs off variations. Who talks to the yard day to day. Who has authority to spend the contingency. On too many refits these questions get answered by accident, halfway through, after a misunderstanding has already cost money. Answer them in writing before the boat hauls out.
Find vetted refit trades in one place, free
Post your refit scope and message background-checked yards, painters, carpenters, electricians and engineers on Yacht Service Network. No commissions, no middleman.
Create your free accountEvery refit that goes wrong went wrong at the spec stage, even when the symptoms only showed up later. A vague scope produces a vague quote, and a vague quote is a trap. The yard prices what it thinks you meant, you assume it priced what you actually wanted, and the gap between those two things becomes a variation order with your name on the invoice.
A usable spec describes the work in enough detail that two different yards would price roughly the same job. That means naming the deliverable, the standard, and the boundary of each item. "Repaint the hull" is not a spec. "Full topsides and superstructure repaint in a two-part polyurethane system, existing fairing assumed sound, includes fairing correction up to 5 percent of surface area, gloss finish to yard's standard sample, masking and reassembly of all deck hardware included" is a spec. The second version can be priced, argued about, and held to. The first cannot.
Break the refit into work packages: hull and paint, teak decks, interior joinery, upholstery, engines and gensets, electrical and electronics, plumbing and tankage, hydraulics, rig if it is a sailing yacht, and general engineering. For each package write down what you want done, the standard you expect, and what you are explicitly not asking for. The "not asking for" list matters more than owners expect, because it is where assumptions hide.
Survey before you spec, not after. A condition survey and, for older steel or aluminium hulls, an ultrasonic thickness survey will tell you what you are dealing with before you commit numbers to paper. Money spent on survey and inspection here is the cheapest money in the entire refit. It converts unknowns into known line items, and known line items can be planned and priced. If the interior is coming out anyway, get behind the panels and look at the systems while access is easy. The worst variations come from things nobody looked at because looking was inconvenient.
If your refit includes a full interior rework, treat the design as its own discipline with its own drawings, materials schedule, and sign-off. A refreshed saloon or new guest cabins can transform a boat, but only if the design is locked before joinery starts. You can find specialists for exactly this through interior design refit providers, and pinning the design early stops the single most expensive kind of change: the one where finished joinery gets ripped out because the owner saw the space and changed their mind.
Once the scope is written, you have to decide how you are paying for it. The two main structures are fixed price (also called lump sum) and time and materials (also called cost-plus). Most real refits end up as a mix, and knowing which structure to apply to which package is one of the highest-value decisions in the whole job.
A fixed-price contract gives you budget certainty. You agree a number, the yard delivers the defined scope for that number, and the risk of the work taking longer than expected sits with the yard. The catch is that the yard prices that risk into the number. For a well-defined package on a boat whose condition is known, fixed price is usually the better deal because the yard's risk premium is small and your certainty is worth a lot. Paint is a classic fixed-price package: the process is well understood, the yard has done it a hundred times, and you want a guaranteed finish for a guaranteed price.
Time and materials means you pay for the hours worked and the materials used, plus a markup. It is cheaper on paper because you are not paying a risk premium, but it demands real oversight. Without someone checking hours, verifying that materials match the job, and questioning slow progress, a cost-plus package drifts. Time and materials makes sense where the scope genuinely cannot be defined in advance: opening up an old engine room, chasing a corrosion problem, or any investigative work where nobody yet knows how bad it is. Trying to fix-price genuinely unknown work just means the yard either gouges you on the premium or gets burned and cuts corners. Neither helps you.
The practical answer for most refits is to fix-price everything you can define, run the genuinely unknown items as time and materials with a not-to-exceed cap, and hold a contingency for the rest. Ask the yard to break its quote down to package level so you can see where the money is and compare like for like against a second yard. A single lump sum with no breakdown is a number you cannot manage. Insist on the itemisation before you sign anything.
Compare yards and trades side by side
Get itemised interest from multiple vetted yards and contractors, message them directly, and keep every quote in one place. YSN is free for owners and captains during beta.
Create your free accountThe contract is where good intentions become enforceable. A handshake and a quote is fine for a bottom clean. It is not fine for a job worth six or seven figures where the boat will be in someone else's shed for months. Get a written contract that names the scope (by reference to your spec and drawings), the price and structure per package, the schedule with milestone dates, the payment terms, the variation process, the quality standard, and the handover conditions.
Payment should follow progress, not the calendar. Milestone payments tied to completed and verified stages keep the yard's interest aligned with yours and stop you from paying for work that has not happened. A workable structure on a substantial refit is a deposit on signing (often 10 to 20 percent to secure the slot and buy long-lead materials), then staged payments released against defined completions: haul-out and strip-out done, systems removed and inspected, major installation complete, fairing and paint signed off, sea trials passed, and a final retention released only after snagging is closed.
Hold a retention. Keeping back 5 to 10 percent of each package until the punch list is cleared is standard practice and it is the single strongest lever you have at handover. Yards work through snagging much faster when the last payment is attached to it. Without retention, the incentive to fix the small stuff evaporates the moment the big invoice is paid, and you spend the next six months chasing defects by email.
Get the insurance and liability terms straight before the boat moves. Who insures the hull while it is in the yard. What the yard's liability cap is if something goes wrong during the work. What happens if the yard's subcontractor damages your boat. These clauses are boring right up until the day you need them, at which point they are the only thing that matters. Read them, or have someone read them for you before signing.
A refit schedule is not a wish. It is a model of how the work actually connects. The core tool is the critical path: the sequence of tasks where any delay pushes the whole finish date back. Some jobs can slip a week with no effect on the end date because other work fills the gap. Others cannot slip an hour without moving everything behind them. Knowing which is which is the whole game.
Build the schedule from milestones and then test the critical path against them. A typical set of milestones runs: design freeze, materials ordered, haul out, strip-out complete, systems removed and surveyed, structural work closed up, major systems installed, fairing complete, paint complete, class and flag inspections passed, recommissioning, sea trials, and redelivery. The big jobs that dominate the timeline (full paint, teak decks, interior joinery, any structural extension) sit on the critical path and everything else has to be sequenced around them.
Paint is usually the critical-path king on a motor yacht refit because it needs a clean, controlled, tented environment and it cannot overlap with dusty or dirty trades. Nothing that generates dust or swarf can happen near fresh fairing or topcoat, which means grinding, welding, and heavy engineering have to finish before paint starts. If your paint scope is significant, plan the whole job backward from the paint window. For the paint package specifically, work with specialists in yacht painting who can tell you the real cure and recoat times, because those times are fixed by chemistry and no amount of schedule pressure changes them.
Timing the yard period matters as much as the internal sequence. In the Mediterranean the main refit season runs October to April, and the good slots fill over the previous summer. Book late and you either take a worse slot or wait a year. In the United States, yards in Fort Lauderdale, Savannah, and the Gulf Coast run year round but the winter season is busiest as boats reposition. Get your slot confirmed early, in writing, because a schedule that assumes yard availability you have not actually booked is fiction.
A realistic programme accounts for supplier lead times, limited crew access during dirty phases, specialist subcontractor availability, weather exposure for anything done outdoors, rework, inspection delays, and final snagging. Every one of those is a place the schedule can slip. Build float into the plan deliberately rather than pretending the job will run to the day. It will not.
Contingency is not a slush fund and it is not an admission of poor planning. It is the line item that acknowledges you cannot see inside a boat until you open it. Every experienced refit manager carries one, and the size of it scales with how much you do not know.
The rule of thumb that holds up across the industry: for a well-planned refit on a relatively new, well-documented yacht, 10 percent is a prudent minimum. For a typical refit with a mix of defined and investigative work, 15 to 20 percent is sensible. For an older vessel being opened up for the first time in many years, 20 to 25 percent is appropriate, and some managers carry more. The less you know about what is behind the panels, the bigger the number should be.
Keep the contingency visible and controlled. It is not part of the package budgets and it is not for scope you simply forgot to price. It is for genuine surprises: the corrosion you find under the tank, the wiring that turns out to be non-compliant, the substrate that needs more fairing than the survey suggested. Every draw against contingency should be a decision, logged and approved by whoever holds that authority, so that by the end of the job you know exactly where it went and why. A contingency that gets quietly absorbed into package overruns tells you nothing and protects nobody.
Keep your whole refit in one place
Owners and captains use Yacht Service Network to source trades, track quotes, and manage the vessel through the job. Free to join and message during beta.
Create your free accountRefits vary enormously in length, from a two-week haul-out and antifoul to an 18-month rebuild. The phases below are the common structure, with indicative durations for a mid-size motor yacht (roughly 30 to 45 metres) going through a substantial refit including paint. Scale the numbers up or down for your boat, but keep the sequence, because the dependencies are real.
| Phase | What happens | Indicative duration | Watch out for |
|---|---|---|---|
| 1. Planning and spec | Survey, scope definition, drawings, budgeting, yard selection, contract | 3 to 9 months before haul-out | Rushing the spec to hit a slot; unpriced assumptions |
| 2. Long-lead ordering | Order paint, teak, engines, generators, custom parts before the boat arrives | Overlaps planning; 2 to 6 months lead | Items that arrive late and stall the critical path |
| 3. Haul-out and strip-out | Boat out of water, interior and systems removed, access opened | 2 to 4 weeks | New defects found once panels are off (contingency time) |
| 4. Structural and systems | Steel or composite repairs, engine and system installs, wiring, plumbing | 6 to 16 weeks | Corrosion, non-compliant old work, inspection delays |
| 5. Fairing and paint | Fairing, primer, topcoat in a controlled tent; no dirty trades nearby | 8 to 14 weeks | Weather, humidity, cure times that cannot be shortened |
| 6. Joinery and interior | Cabinetry, upholstery, flooring, finishes, interior fit-out | 6 to 20 weeks (often parallel) | Late design changes; finish quality on show surfaces |
| 7. Commissioning | Reassembly, systems testing, class and flag inspections | 3 to 6 weeks | Snags that only appear when systems run under load |
| 8. Sea trials and handover | Trials, punch-list resolution, crew briefing, redelivery | 2 to 4 weeks | Open snags at redelivery; retention not yet released |
Notice how much happens before the boat reaches the yard. Half of good project management is front-loaded into planning and ordering. By the time steel is being cut, the important decisions are already made or already lost. For a fuller cost picture across different scopes, our yacht refit guide and costs breaks down what each of these phases tends to add up to, and where owners most often get caught out.
A refit is run in meetings, or it is not run at all. The rhythm that works is a short daily site walk and a weekly review. The daily walk is fifteen minutes with the yard project manager, on the boat, looking at the actual work: what got done yesterday, what is planned today, and what is blocked. It is not a status email. You have to see the work, because photos and verbal updates hide problems that a walk reveals in seconds.
The weekly meeting is where you review the whole picture: progress against the schedule, spend against budget, the status of every open variation, the long-lead item tracker, and any decisions the yard needs from you to keep moving. Keep minutes. Write down every decision, who made it, and the date. A refit generates hundreds of small decisions and memory is not a record. When a dispute comes up in month four about what was agreed in month one, the minutes settle it and nothing else does.
The most valuable question in either meeting is "what are you waiting on from me?" Yards stall constantly on owner decisions: a fabric choice, a fixture approval, a go-ahead on a variation. Every day the yard waits on you is a day added to the job, and it will be a day you get billed for one way or another. Being a fast, clear decision-maker is one of the biggest contributions an owner or captain makes to keeping a refit on schedule.
Variations are the changes that arise once work uncovers what is actually inside the boat, plus the changes you decide you want along the way. They are unavoidable. The goal is not zero variations, it is zero uncontrolled variations. Every change goes through the same process: raised in writing, described, priced by the yard, and approved (or rejected) by the owner's side before the work happens. Written, priced, approved, dated. No exceptions, no verbal go-aheads, no "just do it and we'll sort the cost later."
The "sort it later" trap is where refit budgets die. A verbal yes to a small extra, repeated forty times over five months, becomes a five-figure surprise at the end with no paper trail to argue against. Insist that no variation work starts without a signed variation order, even under time pressure. If the yard genuinely cannot wait for approval on something urgent, agree a fast-track process in the contract with a not-to-exceed cap, so even the urgent stuff has a ceiling.
Keep a live variation register: number, description, quoted cost, status, approval date, and running total. Review it every week. The register is your early warning system. When the total starts eating into contingency faster than the job is progressing, you know you have a problem while you can still do something about it. Track it against contingency explicitly so the two numbers are always in the same view.
Message vetted engineers and trades directly
Need a second opinion on a variation or a specialist for one package? Find and message background-checked marine pros on YSN, free, and keep the conversation on record.
Create your free accountQuality control is not something you do at the end. It is something you do continuously, because defects are cheap to fix while the work is open and expensive to fix once it is closed up. Inspect at the stages where problems are still accessible: check fairing before primer goes on, check wiring before panels close, check substrate before paint. A defect caught at the right stage is a five-minute fix. The same defect caught after handover is a warranty dispute and a return trip to the yard.
Agree the quality standard up front and make it objective wherever you can. "To a good standard" is an argument waiting to happen. A reference sample for the paint finish, a named standard for the teak caulking, a tolerance for panel gaps: these turn subjective disagreements into measurable facts. When the standard is written and referenced in the contract, snagging becomes a checklist instead of a negotiation.
Snagging (also called the punch list) is the systematic walk-through near the end where every defect and unfinished item gets logged, numbered, photographed, and tracked to closure. Do it thoroughly and do it before you release the retention. Walk the whole boat with the yard project manager, list everything, agree which items are the yard's responsibility, and set dates for each. Then do not sign off the list until every item is genuinely closed, not "will be done next week." The retention you held back is what makes this stick. Once the money is gone, so is the urgency.
Line up your specialists early
Find and message vetted painters, teak specialists, upholsterers and electronics integrators on Yacht Service Network before your slot fills. Free for owners and captains.
Create your free accountMost refits involve specialists the yard does not employ directly: paint teams, teak specialists, upholsterers, electronics integrators, specific engine engineers. These subcontractors can be managed by the yard or contracted directly by the owner, and the choice matters. Yard-managed is simpler because the yard coordinates and carries the responsibility, but you pay a markup and lose some direct control. Owner-direct saves the markup and gives you control but means you or your project manager takes on the coordination and the risk of things falling between the cracks.
Whichever way you go, the interfaces between trades are where things go wrong. The painter needs the engineers finished and the shed clean. The upholsterer needs the joinery done. The electronics integrator needs the electricians to have run the cable. Every one of those handoffs is a place for delay and finger-pointing. Map the dependencies explicitly and make one person responsible for each handoff, so that when the painter is ready and the shed is not clean, there is a name attached to fixing it.
Long-lead items deserve their own tracker and their own attention from day one. Paint, teak, engines, generators, custom glass, bespoke hardware, and specialist electronics can carry lead times of two to six months, and a single late item can stall the entire critical path while everyone else stands around. Order long-lead materials before the boat even arrives if you can, confirm delivery dates in writing, and chase them relentlessly. The most avoidable refit delay in the world is a boat sitting finished in every respect except the one part that nobody ordered early enough.
Vet your trades properly before they touch the boat. Check references, look at recent comparable work, and confirm certifications and insurance. A cheap subcontractor who does poor work is the most expensive kind, because you pay twice: once for the bad work and again to have it redone. Our size-by-size look at what refits actually cost, the yacht refit cost breakdown by size, gives a sense of where the money concentrates by trade, which helps you decide where to spend on quality and where a mid-market option is fine.
The table below shows a simplified budget for a substantial mid-size motor yacht refit including a full paint job, so you can see how the packages, project management, and contingency fit together. The percentages matter more than the absolute figures, because they scale. Your numbers will differ, but the shape of the budget, and especially the size of the contingency line, should look broadly like this.
| Budget line | Share of base scope | Notes |
|---|---|---|
| Hull and superstructure paint | 25 to 35% | Usually the single biggest and most critical-path package |
| Interior joinery and finishes | 15 to 25% | Highly variable; driven by how much you rework |
| Engines, gensets and mechanical | 10 to 20% | Overhaul versus replace makes a big difference |
| Electrical, electronics and AV | 8 to 15% | Integration labour often exceeds hardware cost |
| Teak decks | 5 to 12% | Repair versus full replacement; long lead on timber |
| Plumbing, HVAC and tankage | 5 to 10% | Often uncovers hidden corrosion once opened |
| Yard fees, haul-out, berthing, power | 5 to 10% | Time-based, so overruns hit here directly |
| Project management | 1 to 5% | 1 to 3% owner's rep on refit; more on new build |
| Contingency | 15 to 25% on top | Held separately; drawn only on approved surprises |
Read that last row carefully. The contingency sits on top of the base scope, not inside it. If your base packages add up to 1 million, a 20 percent contingency means you are planning for a 1.2 million total and you have not overspent if you use it. Owners who fold contingency into the headline number and then treat any draw as a failure end up in conflict with their own yard over money that was always going to be needed. Plan for the overrun and it stops being a crisis.
Paint deserves a special mention in any refit budget because it is so often the largest single line and the one most sensitive to the choice of system. The difference between paint systems shows up in cost, durability, and finish, and it is worth understanding before you sign. Our comparison of the leading options, yacht paint systems: Awlgrip and Alexseal, walks through what you are actually buying and why the premium systems cost what they do.
Run the numbers with the right people
Post your refit and get itemised interest from vetted yards and trades so your budget is built on real quotes, not guesses. Free for owners and captains on Yacht Service Network.
Create your free accountThe refit is not over when the paint dries. It is over when the boat is redelivered fully operational, to the agreed standard, with the paperwork complete and the snag list closed. A structured handover protects everything you spent the previous months building. Rush it, and the small unfinished items you waved through at redelivery become the problems that follow you around all season.
A proper handover covers the completed works signed off against the spec, the test and commissioning records for every system, the punch-list status with any remaining items dated and owned, all certificates and class and flag documentation, warranties and manuals for new equipment, and a crew briefing on anything new or changed. Sea trials happen before handover, not after, so that anything that only shows up under real load, at speed, or with systems running together, gets caught while the yard is still on the hook.
Hold the retention until the punch list is genuinely closed. This is worth repeating because it is the single most common place owners give away their strongest position. The moment you sign off and release the final payment, the yard's incentive to chase the last ten items drops to near zero. Keep the retention attached to a closed list and those items get done. It is not about mistrust, it is about aligned incentives, and every good yard understands the logic.
Keep the full record after handover too. Every drawing, spec, variation order, test record, and warranty is an asset. It makes the next refit easier, supports the boat's value at sale, and settles any warranty question later. A well-documented refit is worth more than an identical undocumented one, because the buyer knows exactly what was done and to what standard. The YSN app lets owners and captains keep vessel records, service history, and pro contacts in one place on the phone, which means the refit file does not live in a drawer somewhere it will never be found again.
If you run a shipyard, refit yard, or specialist trade, the owners and captains reading guides like this one are the people looking for you right now. Being listed where they search, with your real capabilities and recent work visible, is how the right jobs find you.
Yards and refit trades: list your business free
Get found by owners and captains planning refits. Create a free Yacht Service Network business listing, show your yard's capabilities and recent projects, and receive enquiries directly. Free during beta, no commissions.
List your yard freeRunning a refit well is not about luck. It is about a defined scope, the right contract structure per package, payment tied to progress, a schedule built around the real critical path, weekly control of variations and budget, quality checked while the work is still open, and a handover that does not release the money until the job is finished. Do those things and you will not eliminate surprises, but you will absorb them without the project running away from you.
The overrun statistics are not a warning that refits are doomed. They describe what happens when the discipline above is missing. Owners who plan for a 15 to 25 percent contingency, hold their variations to a written process, and keep their retention until snagging is closed are the ones who look back on a refit as a good decision. The tools are simple. The hard part is applying them every week, from the spec stage right through to redelivery.
Plan for 15 to 25 percent on top of your base scope for most refits. Ten percent is a defensible minimum only for a newer, well-documented boat with a tightly defined scope. For an older vessel being opened up for the first time in years, budget 20 to 25 percent or more, because you cannot see what is behind the panels until the work starts and the surprises there are usually expensive.
Use fixed price for any package you can define clearly, such as paint or a known engine overhaul, because you get budget certainty and the yard's risk premium is small. Use time and materials with a not-to-exceed cap for genuinely investigative work where nobody yet knows the extent, such as chasing corrosion. Most real refits are a mix, and asking the yard for a package-level breakdown lets you apply the right structure to each item.
The two main causes are hidden condition and uncontrolled variations. You cannot fully assess a boat until you open it up, so genuine surprises are normal, which is what contingency is for. The avoidable overruns come from scope creep and verbal change requests that never get priced or tracked. It is common for final costs to land 20 to 30 percent over the initial estimate, which is exactly why a proper contingency and a strict variation process matter so much.
It ranges from a two-week haul-out and antifoul to an 18-month rebuild. A substantial mid-size motor yacht refit including a full paint job typically runs four to nine months in the yard, plus several months of planning and long-lead ordering beforehand. Paint and interior work usually set the critical path, so the size of those packages drives the overall timeline more than anything else.
A variation order is a documented change to the agreed scope: raised in writing, described, priced by the yard, and approved by the owner's side before the work starts. It matters because uncontrolled changes are the fastest way to blow a refit budget. Insisting that every change is written, priced, approved, and dated before work begins gives you a paper trail and a running total, so you always know where the money is going.
Not always, but someone has to do the job whether or not you pay a specialist. On a large or complex refit an owner's representative typically costs 1 to 3 percent of the refit value and usually saves more than that fee through better pricing, schedule control, and stopping scope creep. On a smaller job an organised captain can run it, provided they have the time and the discipline to hold the process together every week.
Build the schedule around the real critical path, book your yard slot early in writing, order long-lead items before the boat arrives, and be a fast decision-maker so the yard never stalls waiting on you. Run a short daily site walk and a weekly review against the schedule and budget. Most delays come from late materials, slow owner decisions, and interface problems between trades, and all three are manageable if you watch them every week.
Handover means the boat is redelivered fully operational and to the agreed standard, with completed works signed off, test records provided, the snag list closed, and all certificates, warranties, and manuals handed over. Sea trials happen before handover so problems that only appear under load get caught while the yard is still responsible. Hold back a retention of 5 to 10 percent until every snag is genuinely closed, because that final payment is your strongest lever for getting the last items finished.